Key Information

Project Name: Bellinger River District Hospital (BRDH) Carpark Upgrade and Extensions

Key Project Information: Earthworks, roadworks, gabion retaining walls, electrical works, footpaths

Client: Mid North Coast Local Health District

Value: $2.6 Million

Duration: 30 weeks

Works Description

  • Stormwater Drainage
  • Gabion Retaining Wall Construction
  • Foundation Preparation
  • Bulk Earthworks
  • Pavement Construction & Kerbing
  • Subsoil Drainage
  • Concrete Footpath & Staircase Construction
  • Lighting & CCTV Installation
  • Bollards, Signage & Linemarking

Client Feedback

AJCP were able to manage the project seamlessly in face of the site access challenges, and unexpected site conditions that arose during the Contract and were responsive to requests for information and suggested improvements to safety, quality, and environment.

AJCP’s performance was consistent across the life of the project and the team worked cooperatively with the Principal in achieving an end product that meets time, cost and quality objectives.

Robert Spampinato
Project Manager
North Coast Region, Public Works Advisory, Department of Regional NSW